CORENET X from 1 October 2026: what changes for M&E submissions

CORENET X is mandatory from 1 October 2026 for new projects of 5,000 m² GFA and above. What the gateway process means for mechanical engineers and building owners.

Written by CVC Engineers · · 5 min read

The dates

  • 1 October 2025: CORENET X mandatory for new projects of 30,000 m² GFA and above.
  • 1 October 2026: mandatory for new projects of 5,000 m² GFA and above (joint URA and BCA circular, July 2026).
  • Smaller projects may opt in and can continue on CORENET 2 for now. Projects of 5,000 m² and above that began CORENET 2 submissions by 30 September 2026 may continue there.

CORENET X is Singapore's coordinated regulatory submission platform for building works. It replaces the old approach, in which each agency received and processed its own submissions, with a joint process organised around project gateways. Agencies including BCA, URA, SCDF, PUB, NEA, LTA and NParks review the submission together at each gateway.

Why it matters to M&E

What owners should do

Implementation details are still evolving. Always check the latest URA and BCA circulars before you finalise a submission strategy.

Frequently asked questions

When is CORENET X mandatory?

From 1 October 2026, for new projects of 5,000 m² GFA and above, under the joint URA and BCA circular of July 2026. It has been mandatory for new projects of 30,000 m² and above since 1 October 2025. Smaller projects may opt in.

Can small projects still use CORENET 2?

Yes, for now. Under the July 2026 circular, projects below 5,000 m² GFA may submit through CORENET X voluntarily and can continue using CORENET 2.

Sources

  1. URA circular DC26-08: Updates to CORENET X implementation plan
  2. URA circular DC25-07: CORENET X mandatory submissions from 1 October 2025